Built as a nuclear-powered fast attack submarine under yard no 256 by General Dynamics Electric Boat, Groton, Connecticut for the USA Navy.
29 June 1996 ordered.
05 December 1998 laid down.
13 May 2004 launched as the USS JIMMY CARTER (SSN23) a modified Seawolf-class submarine.
05 June 2004 christened by former First Lady Rosalynn Carter.
Displacement: 7,568 tons light,12,139 tons full, and 1,569 tons dead. Dim. 138 x 12.1 x 10.9m (draught surfaced.) Waterline length 128.5m.
Propulsion: 1 S6W PWR 57,000 shp (43 MW), HEU 93.5%, 1 secondary propulsion submerged motor, 1 shaft, 1 pump-jet propeller. Speed 40 knots.
Armament: 8 × 26 in (660 mm) torpedo tubes, Boeing Harpoon missiles, BGM-109 Tomahawk missiles, Mark 48 torpedoes. Ability to lay mines.
Crew 141.
19 February 2005 commissioned homeport Bangor Annex of Naval Base Kitsap, Washington.

USS JIMMY CARTER (SSN-23) is the third and final Seawolf-class nuclear-powered fast-attack submarine in the United States Navy. Commissioned in 2005, she is named for the 39th president of the United States, Jimmy Carter, the only president to have qualified on submarines. The only submarine to be named for a living president, JIMMY CARTER is also one of the few vessels, and only the third submarine of the US Navy, to be named for a living person. Extensively modified from the original design of her class, she is sometimes described as a subclass unto herself.

Construction
The contract to build JIMMY CARTER was awarded to the Electric Boat Division of General Dynamics Corporation in Groton, Connecticut on 29 June 1996, and her keel was laid on 5 December 1998. Original schedules called for JIMMY CARTER to be commissioned in late 2001 or early 2002. Electric Boat was awarded an $887 million extension to the JIMMY CARTER contract on 10 December 1999 to modify the boat for testing new submarine systems and classified missions previously carried out by USS PARCHE. During modification, her hull was extended 100 feet (30 m) to create a 2,500-ton supplementary middle section which forms a Multi-Mission Platform (MMP). This section is fitted with an ocean interface for divers, remotely operated vehicles (ROVs), and special operation equipment; ROV handling system, storage, and deployment space for mission systems, and a pressure-resistant passage between the fore and aft parts of the submarine to accommodate the boat's crew.
JIMMY CARTER was christened on 5 June 2004, and the ship sponsor was former First Lady Rosalynn Carter. One result of the changes was that JIMMY CARTER was commissioned more than six years after USS CONNECTICUT and almost four months after the commissioning of USS VIRGINIA, the first of the Virginia-class subs.
JIMMY CARTER has additional maneuvering devices fitted fore and aft that allows her to keep station over selected targets in odd currents. Intelligence experts speculate that the MMP may find use in missions as an underwater splicing chamber for optical fiber cables.
Deployments
On 19 November 2004 JIMMY CARTER completed alpha sea trials, her first voyage in the open seas. On 22 December, Electric Boat delivered JIMMY CARTER to the US Navy, and she was commissioned 19 February 2005 at NSB New London.
JIMMY CARTER began a transit from NSB New London to her new homeport at the Bangor Annex of Naval Base Kitsap, Washington on 14 October 2005 but was forced to return when an unusually high wave caused damage while the submarine was running on the surface. The damage was repaired and JIMMY CARTER left New London the following day, arriving at Bangor the afternoon of 9 November 2005.
In April and September 2017 JIMMY CARTER returned twice to her homeport at Naval Base Kitsap-Bangor, flying a Jolly Roger flag, traditionally indicative of a successful mission.

2022 In active service.

https://en.wikipedia.org/wiki/USS_Jimmy_Carter
Sierra Leone 2018 9800Le sg?, Scott 3310
Attachments
Jimmy_Carter_SSN_23 (2).jpg
Jimmy_Carter_SSN_23 (2).jpg (105.22 KiB) Viewed 480 times
2018 jimmy carter  Submarines (3).jpg
2018 jimmy carter Submarines (3).jpg (59.89 KiB) Viewed 480 times

Post Reply